If 40 men working 13 hour per day can complete a piece of work in 20 days then how many hours per day can 26 men complete the same work in 25 days?
1
12 hours
2
14 hours
3
16 hours
4
18 hours
5
20 hours
If 40 men working 13 hour per day can complete a piece of work in 20 days then how many hours per day can 26 men complete the same work in 25 days?