A can finish a work in 6 days. B can finish a work in 10 days. What is the ratio of the amounts that A and B would be paid for the same amount of work if they finish it individually. 

1
3 : 4
2
4 : 5
3
5 : 3
4
2 : 1
5
3 : 2