4 men can complete a piece of work in 3 days. 6 women can complete the same piece of work in 3 days, whereas 3 children can complete the same piece of work in 8 days. 3 women and 4 children worked together for 1 day. If only men were to finish the remaining work in 1 day, how many total men would be required?

1
10
2
8
3
6
4
12
5
9