Identify the correct sequence of Controlling process :
(A) Analysing deviations
(B) Measurement of actual performance
(C) Setting up standards
(D) Comparison of actual performance with standards
Choose the correct answer from the options given below :
1
(A), (B), (C), (D)
2
(A), (C), (B), (D)
3
(B), (A), (D), (C)
4
(C), (B), (D), (A)