A can complete a work in 15 days and B can complete a work in 10 days. If A increases its efficiency by 40% and B increases it by 20% then in how many days will they complete 2/3rd of work?
1
36/8 days
2
46/8 days
3
25/8 days
4
45/8days
5
None of the above