Aman takes thrice the time of Jitu to complete a piece of work, and Jitu takes five times the time of Pawan to complete the same work. If they work together then they can finish the work in 30 days. Then find the time taken by them to complete the work individually?

1
570 days, 190 days, 38 days
2
380 days, 190 days, 38 days
3
570 days, 190 days, 57 days
4
None of these