other govt exam India Post Postman & Mail Guard Mock Test 2020 Quantitative Aptitude Time and Work Work Efficiency
If 15 men construct a building in 50 days, then in how many days can 10 men construct a building?
1
15 days
2
40 days
3
75 days
4
45 days