Ravi, Mohan, and Sachin can do a work in 10 days, 20 days, and x days individually, If Ravi worked for 2 days and Mohan worked for 3 days and the remaining work is completed by Sachin in 26 days, then find the value of x.
1
30 days
2
40 days
3
20 days
4
13 days