other govt exam India Post Postman & Mail Guard Mock Test 2020 Quantitative Aptitude Time and Work Work Efficiency
40 men can finish a work in 15 days. If the work is to be completed 3 days earlier, how many more people should be employed?
1
8
2
3
3
15
4
10