Comprehension Passage

Directions: Answer the questions based on the information given below.

Project Total Assigned Tasks Percentage of Tasks Completed Percentage of Tasks Requiring Rework Within 15 Days of the Total Tasks Completed Total Tasks Requiring Rework
V 60 70% 14.28% 22
W 140 80% 7.14% 12
X 100 75% 6.66% 15
Y 80 90% 11.11% 12
Z 120 80% 16.66% 22

 

If the percentage of tasks not completed for Project W were reduced by 25%, and the total assigned tasks for Project X increased by 20% (while the percentage of tasks completed remains the same), what would be the new difference in the number of tasks not completed between Project W and Project X?

1
8
2
9
3
5
4
4
5
7

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation