The efficiency of Raj is 3/2 times of Suraj’s efficiency and the efficiency of Vijay is 1/3 times of Raj’s efficiency. If the total time taken to complete the whole work if all three of them working together is 16 days, then what is the total time taken by Suraj alone to complete the 3/4 of the total work?
1
30 days
2
32 days
3
34 days
4
38 days
5
36 days