X, Y and Z can do a job in 80, 120 and 160 days respectively. X and Y work together for 24 days and leave the job. In how many days can Z complete the remaining job if his efficiency is halved?
1
125
2
120
3
160
4
150
5
None of the above/More than one of the above.