Comprehension Passage

Directions: Study the following information carefully and answer based on it.

The bar graph given below shows the number of days taken by A alone to complete 4 different projects i.e. P, Q, R, and S and the time taken by A and only one other project partner working together to complete each of the 4 different projects.

Note - (i) B, C, D and E partner up with A for projects P, Q, R and S respectively.

(ii) The efficiency of a given person is the same irrespective of the type of project they work on.



Number of days taken by A and his project partner together to complete the work:-

Project P Q R S
Number of Days  21 17.5 42 35

 

On Project P, if B alone worked for 17.5 days. Then the remaining work can be completed by A alone in how many days ?

1
22 days
2
35 days
3
25 days
4
18 days
5
32 days

Sponsored

hivanix.in

Visit

This quiz is brought to you by hivanix.in

🌐 Web App Development

Quick Navigation