Time taken by P to finish a piece of work is twice the time taken Q and thrice the time taken by R. If all three of them work together, it takes them 9 days to complete the entire work. How much time will 'R' need to finish the work alone?
1
18 days
2
19 days
3
23 days
4
21 Days
5
15 Days