Consider the following statements:
1. Building Information Modeling has the ability to produce 3D CAD model.
2. Sequencing of the construction operations can be studied and the schedule can be incorporated into the BIM model.
3. BIM has the capability of adding what some refer to as the fifth dimension, the verbal definition of installed items.
Which of the above statements are correct?
1
2 and 3 only
2
1 and 2 only
3
1, 2 and 3
4
1 and 3 only