For a large-scale civil engineering project involving the construction of a bridge, the client seeks a contract that provides cost control while allowing for adjustments due to potential design modifications during the project. Which contract type is most appropriate for this situation?
1
Fixed-Price (Lump Sum) Contract
2
Time and Materials (T&M) Contract
3
Cost-Reimbursable Contract
4
Unit Price Contract