The project activities are given in the following table along with the duration and dependency.

Activities

Duration

(days)

Depends on
P 10 -
Q 12 -
R 5 P
S 10 Q
T 10 P, Q


Which one of the following combinations is correct? 

1
Total duration of the project = 22 days, Critical path is Q → S
2
Total duration of the project = 20 days, Critical path is Q → T
3
Total duration of the project = 22 days, Critical path is P → T
4
Total duration of the project = 20 days, Critical path is P → R