state gov AP Police SI (Pre+Mains) Mock Test 2022 Quantitative Aptitude Time and Work Work Efficiency
P alone can complete work in 18 days and Q alone can complete the work in 24 days. P and Q work for 8 days together then Q left the work remaining work will be completed by P in -
1
3 days
2
12 days
3
4 days
4
6 days