state gov RVUNL/JVVNL Junior Assistant / Stenographer Mock Test 2021 Quantitative Aptitude Time and Work Work Efficiency
P is five times as good as Q and together they finish a piece of work in 30 days. The number of days taken by P alone to finish the work is-
1
45 days
2
36 days
3
12 days
4
48 days
5
60 days