Shaffer Company acquires land for Rs. 77,000 cash. Additional said are as follows.
|
Removal of shed |
Rs, 300 |
|
Filling and grading |
Rs, 1,500 |
|
Salvage value of lumber of shed |
Rs, 120 |
|
Broker commission |
Rs. 1,130 |
|
Paving of parking lot |
Rs, 10,000 |
|
Closing costs |
Rs, 560 |
Shaffer will record the acquisition cost of the land as
1
Rs. 77,000
2
Rs. 78,690
3
Rs. 80,610
4
Rs. 80,370