A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
1
8 days
2
10 days
3
6 days
4
9 days
A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.