As per the Rajasthan Municipalities (Purchase of Materials and Contracts) Rules, 1974, consider the following:
| Value of Tender | Time Limit |
| I. For petty works costing up to Rs. 1 lakhs |
10 days |
| II. Work exceeding 1 lakhs but up to 10.00 lakhs | 14 days |
| III. Work exceeding 10 lakhs but up to 100.00 lakhs | 15 Days |
Which of the above is/are correctly matched in the case of tenders for public works?
1
I Only
2
I, II Only
3
III Only
4
I, II, III