As per the Rajasthan Municipalities (Purchase of Materials and Contracts) Rules, 1974, who gives the technical approval of estimates and examination of bills in the stage of construction work up to Rs. 50 lakhs?

1
Junior Engineer
2
Assistant Engineer
3
Executive Engineer
4
Superintending Engineer