A can do a piece of work in 12 days while B alone can do it in 15 days. With the help of C they can finish the work in 5 days. If they are paid Rs 960 for the whole work, how much money A gets?

1
Rs 480
2
Rs 240
3
Rs 320
4
Rs 400
5
Not Attempted