P can complete a work in 12 days and Q can complete a work in 24 days. They started working together, P leaves the work after working for 6 days and rest work is done by Q. If both were to be paid Rs 3000 collectively for the whole work then what is the wage of Q?
1
Rs 1500
2
Rs 2000
3
Rs 2100
4
Rs 2400
5
Rs 1800