A can do a certain work in 70 days. B is 25% less efficient than A and C is 25% more efficient than A. All the three started the work together. If B and A left the work 4 days and 2 days before the completion of the work, respectively, then in how many days was the entire work completed?

1
14 days
2
25 days
3
18 days
4
13 days