P and Q can do a piece of work in 20 and 30 days respectively. They start working together then left after 5 days and the remaining work is completed by R in 4 more days. If they get Rs. 6000 at the end then find the share of R.
1
Rs. 3500
2
Rs. 1000
3
Rs. 3000
4
Rs. 1500
5
Rs. 2500