A and B can do a piece of work in 10 and 15 days respectively. A alone did the work for 4 days and then B did it for 5 days. Thereafter C did the remaining work in 8 days. How long will they take to complete the work together?

1
8 days
2
5 days
3
3 days
4
7 days