A group of workers including 10 men and 5 women can finish certain amount of work in 25 days. If the women in the group are replaced by men, then the work can be finished 5 days earlier. The wages are Rs 500/day for men and Rs 400/day for women. How much does it cost when 13 men and 7 women finished the entire work?

1
Rs. 176700
2
Rs. 160000
3
Rs. 154700
4
Rs. 155660