Devendra can complete a piece of work in 20 days, while Ishwar can complete the same work in 25 days. If they start with Devendra and work in turns, skipping one day each, then how many days will it take to complete the work?
1
24\(\frac{4}{5}\) days
2
22\(\frac{1}{5}\) days
3
23\(\frac{2}{5}\) days
4
25\(\frac{3}{5}\) days