state gov APPSC Group 4 (Pre+Mains) Mock Test 2022 Quantitative Aptitude Time and Work Work Efficiency
P can do a work in 8 days. Q can do the same work in 24 days. Both together worked for 5 days and P left the job. How many days will Q take to complete the remaining work?
1
12 days
2
8 days
3
4 days
4
10 days