state gov Patna Civil Court Clerk/Reader Mock Test Series Quantitative Aptitude Time and Work Work Efficiency
36 workers can complete a work in 12 days. How many workers are to be joined with these workers finish the work before 3 days.
1
48
2
36
3
24
4
12