state gov UP Police Head Operator (Radio Cadre) Mock Test Quantitative Aptitude Time and Work Work Efficiency
X can complete 1/2 the task in 8 days and Y can complete 1/4th of the task in 16 days. In how many days together can they finish the task?
1
12.5
2
12.8
3
12.2
4
10.8