A can do work in 6 days. B takes 8 days to complete the work. C takes the time equal to the time taken by A and B to work together to complete that task. If B and C work together, how much time will they take to complete the work?

1
\(\frac{{13}}{5}\) days 
2
\(\frac{{14}}{5}\) days 
3
\(\frac{{12}}{5}\) days 
4
\(\frac{{11}}{5}\) days 