A and B together can finish a work in 36 days. A and C take \(7 \frac{3}{11}\) days more to complete the same work than that of B and C. A, B and C together complete the work in 24 days. In how many days will A, B and C finish it separately?
1
60, 72, 90
2
60, 90, 72
3
72, 60, 90
4
90, 60, 72