Among the following, the correct sequence of WBM construction will be:
i. Preparation of subgrade
ii. Spreading of Coarse aggregates
iii. Application of binding material
iv. Application of screenings
v. Provision of lateral confinement
1
i, ii, iv, iii, v
2
i, iv, ii, iii, v
3
i, v, ii, iv, iii
4
ii, i, iv, v, iii