A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete \(\frac{4}{9}\) part of the original work in:
1
24 days
2
12 days
3
20 days
4
16 days