Which one of the following statements is NOT correct according to Gantt chart?
1
Activities are illustrated as bars on a horizontal time line.
2
Beginning and end of a bar coincides with the activity's starting and ending dates.
3
The time and operational con- currency aspects of the schedule is missed in this chart.
4
Illustrations are given that how the activities are to be distributed over the project time line.