Crash project duration is obtained by summing the
1
Normal durations for all the activities
2
Crash durations for all activities.
3
Crash durations for all the activities along the critical path were obtained by taking into account the normal duration for all the activities
4
Crash durations for all the activities along the critical path are obtained by taking into account the crash duration for all the activities.