Which of the following activity is non-critical in the project given in the table below?

Activity Predecessor Duration Cost slope Workers/day
P -- 3 20 5
Q -- 4 30 4
R P 4 25 4
S P, Q 3 25 5
T R 3 15 5
U R, S 4 55 4

1
P
2
R
3
T
4
U