A project takes 20 days along critical path and has a variance of 16 days. What is the probability of completing the project within 18 days?
| Z | 0 | 0.5 | 1 |
| Probability | 50% | 69.2% | 84.1% |
1
69.2%
2
30.8%
3
55.95%
4
44.05%