Select the correct AON network diagram for the following project activities:
| Activity | Immediate Successor |
| 1 | 2 |
| 2 | 3, 4 |
| 3 | 5 |
| 4 | 5 |
1
2
3
4
Select the correct AON network diagram for the following project activities:
| Activity | Immediate Successor |
| 1 | 2 |
| 2 | 3, 4 |
| 3 | 5 |
| 4 | 5 |