engineering recuitment APSC AE Civil 2020 Test Series Construction Materials and Management Project Planning CPM
Which system of network given below completely eliminates the use of dummy activities?
1
A – O – A (Activity – on - Arrow)
2
A – O – N (Activity – on - Node)
3
PERT
4
CPM