P and Q can complete whole work in 60/11 days and P can complete whole work alone in 12 days. If Q starts functioning only at 60% of its original capacity then in how many days will P and Q complete the whole work?
1
(88/13) days
2
(500/43) days
3
(86/13) days
4
(300/43) days
5
(105/13) days