engineering recuitment PPSC JE Civil Mock Test 2022 Construction Materials and Management Project Planning PERT
The optimistic, most likely and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion time of this activity is
1
10 days
2
11 days
3
9 days
4
5 days