x and y can complete a work in 12 days and 10 days respectively. With the help of z, x and y together can complete this work in 5 days for a total salary of Rs 6000, So how much salary should z get for his work share?

1
Rs. 550   
2
Rs. 400 
3
Rs. 250 
4
Rs. 500 