Direction: The item consists of two statements, one labelled as the 'Statement (I)' and the other as 'Statement (II)'. You are to examine these two statements carefully and select the answers to these items using the codes given below:

Statement (I): Cross drainage structure, aqueduct is constructed to negotiate an aligned channel over, below or at the same level of a stream.

Statement (II): Aqueduct is constructed, when full supply level (FSL) of canal is much higher than high flood level (HFL) of a stream.

1
Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
2
Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
3
Statement (I) is true but Statement (II) is false
4
Statement (I) is false but Statement (II) is true