engineering recuitment BMC Sub Engineer Mock Test 2024 Construction Materials and Management Project Planning PERT
A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is
1
3
2
√3
3
3√3
4
9
5
18