engineering recuitment DDA JE Civil 2023 Mock Test Construction Materials and Management Estimation and Costing
Mobilization advance up to certain percentage of cost of work is given to a contractor
1
On commencement of work at site for payment of loan taken by him
2
For the purchase of construction materials
3
For the payment of advances to labour and other staff
4
For all activities required to start the work at site on finalization of the contract documents