Select the incorrect statement.:

1
Earliest start of an activity is the early event time of the node it leaves
2
Latest finish of an activity is the late event time of the node it enters
3
Latest start of an activity is its latest finish minus its duration
4
Earliest finish of an activity is the late event time of the node it enters minus its duration